A method to transport a deck at sea and install the deck on an offshore
substructure. The deck is completely fabricated on a set of deep girders.
The deck and deep girders are skidded onto two pontoons. The deck and deep
girders are tied down together. A set of jacking units is installed into
the deep girders prior to sail out. The complete assembly is towed to the
installation site. At the site, the tie downs are removed. The girders are
jacked up and the pontoons simultaneously ballasted down until the
assembly is supported on the pontoons. The deck is lowered onto the
substructure and the pontoons released