In a method and computer program product for optimizing power plant
control values and a power plant optimizing system an optimization module
(1) minimizes total plant operation costs while achieving predetermined
required output values for produced power and process steam. This is done
by, at a given time, determining future values of control values and
simulating, in a simulation module (2), the behavior of the plant up to a
given future time. Corresponding fuel costs and generated power are
determined in the simulation, and incorporated in an objective function.
The optimization module (1) minimizes the objective function by varying
the control values. According to the invention, a rate of ageing of plant
components is determined when simulating the future behavior of the
plant, and the objective function to be minimized comprises said rate of
ageing.