A method of compacting a mat of hot mix asphalt which has been laid by an
advancing asphalt paver, the method comprising advancing an asphalt
compactor over the laid asphalt such that a compaction surface of the
compactor, formed by a lower run of at least one belt, is engaged with
any one portion of the mat for a period of at least 1.5 seconds, the
compaction surface applying a maximum average load stress to the mat of
less than about 50 kPa (7.252 psi). Compaction may be achieved using a
compactor (60) comprising two longitudinally spaced modular compaction
units (62) connected relative to each other, and a power source for
driving at least one of the modular compaction units (62), wherein at
least one of the modular compaction units (62) is adjustable to permit
steering of the compactor, and wherein each of said modular compaction
units (62) comprises a compaction belt (74), support means (78, 80) for
the belt to define a planar lower run of the belt (74) forming a
compaction surface.