A construction process for the composite pile foundation which consists of
the expanded belled base and the pile shaft, the construction process
comprising the steps of: a) Aligning the pile tip at the pile location
and place the casing at the top of the pile tip; b) Lifting the heavy
hammer to enter the casing, repeatedly lift the heavy hammer to reach the
given height and back press the casing, let it fall freely to ram the
pile tip and the soil until a hole forms at the pile location; c) Lifting
the heavy hammer higher than the feed inlet of the casing and fill solid
material from the inlet into the casing; d) Ramming the above-mentioned
solid material and repeat the filling and ramming operations; e)
Controlling the penetration of the last three blows; f) Filling graded
aggregate or stiff consistency concrete and repeatedly ram it to form the
expanded belled base; g) pull out the casing; h) Aligning the pile shaft
at the pile hole and repeatedly back press and blow slightly with the
heavy hammer to drive the pile shaft into the pile bole and fix and
connect it with the expanded belled base; i) Controlling the penetration
of the last three bouts and form the pile. The invention offers the
advantages of high bearing capacity, small settlement, short pile shaft,
low engineering cost, simple construction, short construction period,
easy quality control etc.