A method for calculating availability in line power systems composed of
power circuit modules determines power circuit parameters associated with
the power circuits, accepting input from central databases. The method
calculates a required number of power circuits to complete the line power
system, and calculates the total power to be delivered over the power
system, based on a power calculator. The method calculates individual
power circuit availabilities based on the power circuit compositions and
external variables. The method then calculates an overall system
availability based on the power circuit availabilities and other external
variable inputs. The method may compare the calculated line power system
availability with a target availability, revise the power circuit
parameters, and recalculate the system availability to meet the target
availability.