In the various methods of the present invention, reliance is placed on a first and second barrier 26 and 30 respectively positioned in a well 10 to provide well control during well suspension, completion and/or workover operations. Each of the barriers is below the depth of the lowermost end of a completion string when that string is installed in the well 10. By not placing either barrier higher up in the well-bore, both of the barriers can remain in place during suspension and completion and workover operations, thus obviating the need to use a BOP stack to supplement well control. This results in a considerable saving in drill rig time and thus significantly reduces the cost of constructing a well.

 