A method of placing a concrete compositions including a) combining 3-40
volume percent cement, 5-50 volume percent fine aggregate, 5-50 volume
percent coarse aggregate, and 10-22 volume percent water; b) adding
1.5-40 volume percent of prepuff particles to form a concrete
composition; and c) pumping the concrete composition to a point higher in
elevation than the delivery point of the concrete to place the concrete.
The concrete composition contains less than 30 volume percent of other
light weighting aggregates and the prepuff particles have an average
particle diameter of from 0.2 mm to 8 mm, a bulk density of from 0.02
g/cc to 0.64 g/cc, an aspect ratio of from 1 to 3. The slump value of the
placed concrete measured according to ASTM C 143 is greater than 1 inch
and the concrete has a density of from about 40 to about 135
lb./ft.sup.3.