A method and a device for installing a sub-sea riser for an offshore
operation, between a base installation disposed on the sea bed and a sea
installation protruding above the base installation. The sub-sea riser is
provided with a first end and a second end. The method comprises the
following stages in the following order: a) the first end of the riser is
joined to the sea installation; b) the sub-sea riser is deployed; c) the
second end of the riser is guided towards the base installation; d) the
second end is coupled to the base installation by releasing the second
end and the efforts of the recoil force exerted on the base installation
are transferred; e) the second end and the base installation are
connected to each other.