For laying synthetic underground piping (1) a ground channel (2) is first
bored and the piping (1) is introduced into the ground channel (2). To
facilitate laying an underground pipe length particularly effectively, the
pipe length (1) comprising a hardening synthetic mass is manufactured at
the same time as it is introduced into the ground channel (2) by the
prepared synthetic mass being formed continuously inside the ground
channel (2) as a run of piping (3) and left to harden. A reactor (4) which
can be drawn through the ground channel (2) and comprising a front reactor
drum (5) and a rear double-sheathed calibrating cylinder (6) is provided
for this purpose, whereby reactor drum (5) and calibrating cylinder (6)
are arranged coaxially to one another and relatively rotatably and lines
(8) for supply of constituents terminate in the reactor chamber (51) of
the reactor drum (5) and the reactor chamber (51) is connected by way of a
nozzle ring (12) to the calibrating space, open from below and formed from
the double mantle (10) of the calibrating cylinder (6).